Road Work Update For Week Of April 19, 2021
FOR IMMEDIATE RELEASE
Contact: Tangipahoa Parish President Robby Miller
(985) 748-3211
HAMMOND—While rain delayed some of the overlay work planned last week, Tangipahoa Parish President Robby Miller said crews will be back at work on Monday with a full week of construction plans.
On the schedule for next week’s overlay:
*Asphalt patching is scheduled on Broadwalk, Campbell, Travis, Pleasant Ridge, and East Hoffman, Schum, F. Joiner, Morgan Howes, Live Oak, Brown, and Ciolino;
*Asphalt overlay is scheduled on East Hoffman, Ciolino, and Harden Street Extension;
*Crews will be milling Brown Road, River Crest, R. Harper, Octavia, Freret, and Phoenix Square;
*Shoulder work is planned on Ciolino, Pleasant Ridge, and East Hoffman;
*Soil cement work is scheduled on Campbell Lane.
All work is weather-permitting, Miller said. Signs will be posted on the day of construction, and Miller reminds motorists to use alternate routes, where possible, due to traffic delays during the construction period.
For more information on Tangipahoa Parish road work, go to www.Tangipahoa.org or check out the Tangipahoa Parish Government social media channels on Facebook and Twitter.