Road Work Update for Week Of August 31, 2020

FOR IMMEDIATE RELEASE
Contact: Tangipahoa Parish President Robby Miller
(985) 748-3211

HAMMOND—Tangipahoa Parish President Robby Miller said the parish’s overlay work has reached the punch list phase, with dressing work and finishing touches planned this week, weather permitting.

Miller said the parish contractor has scheduled the following streets for dressing work during the week of August 31:

*On Monday, August 31, crews will dress Pleasant Ridge, N. 7th Street, and Barringer Drive;

*On Tuesday, Sept. 1, crews will dress N. 7th Street, Barringer Drive, Pleasant Ridge, and Professional Plaza;

*On Wednesday, Sept. 2, dressing work continues on Professional Plaza, Brandon Court, and Brandon Drive;*On Thursday, Sept. 3, the contractor will dress Brandon Court, Brandon Drive, Vinyard Trace, Muscarello, and Watson;

*On Friday, Sept. 4, dressing crews will continue work on Watson, Arena, Ogden, and BT Thomas.

Miller said punch list items will also be addressed daily, as weather permits.

All work will be posted on the day of construction. 

For more information on Tangipahoa Parish road work, go to www.Tangipahoa.org or check out the Tangipahoa Parish Government social media channels on Facebook and Twitter.