AMITE—Tangipahoa Parish President Robby Miller announced the following road work is scheduled during the week of July 6:

*On Monday, July 6, crews will be dressing Pleasant Ridge, Emerald Court, Cassidy, and Lakin while milling resumes on Mooney and E. Hanson. Soil cement crews will be working on Vinyard Trace and Falcon;

*On Tuesday, July 7, paving crews will be working on Maryland, Bradon Drive, Brandon Court, and Barnes. Dressing work continues on Hoffman Court, Hoffman Drive, Muscarello and Maryland while milling crews work on Mooney and E. Hanson. Soil Cement work continues on Kelly, Falcon, and Bethel Church Road;

*On Wednesday, July 8, soil cement work is scheduled on Bethel Church Road, Courtney, Earl, Robert Blow Road, and Oak. Paving continues on Maryland, Brandon Drive, Brandon Court, and Barnes while milling work resumes on Watson, Ogden, Arena, and BT Thomas. Milling work is scheduled on Barringer Drive;

*On Thursday, July 9, soil cement work is scheduled on Oak, EA Hoover, Willow Lane, and Magnolia while milling work continues on Barringer Drive and N. 7th Street;

*On Friday, July 10, soil cement crews will be working on Magnolia, Wainwright, Gahn, Hogan, and Oscar Sharkey while milling work continues on Barringer and North 7th Street;

*On Saturday, July 11, crews will perform soil cement work on Professional Plaza.

All work will be posted on the day of construction. 

For more information on Tangipahoa Parish road work, go to www.Tangipahoa.org or check out the Tangipahoa Parish Government social media channels on Facebook and Twitter.

 

Previous Article Press Release: Parish Approved For FEMA Grant
Next Article Road Work Update Week of July 11- 18, 2020
Print
5297
CategoryNews & Notices

Theme picker